Data Centers, Power Bills and Who Pays for the AI Buildout
Why a 2024 grid auction sent capacity prices soaring as data centers multiplied, how those costs reach household bills, and the case for making big tech pay for the power it needs.
Most people have never heard of a capacity auction, and until July 2024 there was little reason to. That month, PJM Interconnection, the nonprofit that runs the electric grid for all or part of thirteen states and Washington, D.C., released the results of its annual auction for the 2025-26 delivery year. The auction sets what utilities pay power plants simply to be available on the hottest and coldest days. In the previous auction, the price had cleared at about $29 per megawatt-day across most of the region. This time it cleared at about $270. The total cost to consumers jumped from roughly $2.2 billion to roughly $14.7 billion in a single year. Utility regulators from New Jersey to Ohio started warning households that bills would rise the following summer, and they did. Many reasons fed into the jump, including power plant retirements and rule changes. But one stood out in every analysis: a wave of new demand from data centers, the warehouse-sized buildings full of computers that train and run artificial intelligence. The question that auction raised has not gone away. When a handful of the richest companies on earth need enormous new amounts of electricity, who should pay for it?
In short: The AI boom is driving the fastest growth in electricity demand in a generation, and grid costs tied to it are showing up in ordinary families' bills. Here's the argument: the companies building data centers can afford to pay the full cost of the power and grid upgrades they require, and state regulators should make them. Done right, this is not anti-technology; it is basic fairness in how a public utility system shares its costs.
How an auction reaches your kitchen
To see why a technical grid auction matters, it helps to know how your bill is built. An electric bill pays for three broad things: the energy itself, the wires that carry it, and the assurance that enough power plants will be ready when demand peaks. That third piece is what PJM's capacity market buys. Power plants bid to be available years ahead; the auction picks a single clearing price, and utilities pass the cost to customers.
When the clearing price rises nearly tenfold, the increase does not stay inside the industry. It is spread across everyone who buys power in the region, which includes tens of millions of people, from row houses in Baltimore to farmhouses in rural Pennsylvania to apartments in Chicago's suburbs. Households cannot negotiate. They pay what the utility commission approves.
The following year's auction, for 2026-27, cleared at a price cap that had been put in place after Pennsylvania Governor Josh Shapiro challenged the market's design. Without that cap, prices would have gone higher still. PJM's independent market monitor, the outside watchdog that reviews its markets, has attributed a large share of the increases to current and forecast data-center demand.
Why demand is suddenly climbing
For about fifteen years, electricity use in the United States was nearly flat. Efficient lighting, better appliances and a shift away from heavy industry offset population and economic growth. Utilities planned for a world where demand barely moved.
That world ended quickly. A December 2024 report from the Lawrence Berkeley National Laboratory, prepared for the Department of Energy, estimated that data centers used about 4.4 percent of US electricity in 2023 and could use between about 7 and 12 percent by 2028. Training large AI models and serving millions of user requests takes enormous computing power, and computing power takes electricity, both to run the chips and to cool them.
Northern Virginia, especially Loudoun County, has the largest concentration of data centers in the world, and sits inside PJM. Data-center campuses are also rising in Ohio, Pennsylvania, Texas, Georgia, Arizona and elsewhere. Some single projects ask utilities for as much power as a mid-sized city uses.
Forecasting this demand is hard, and that uncertainty is itself part of the cost problem. Developers often shop the same project to several utilities at once, looking for the fastest connection, so the requests utilities report can double-count projects that will be built in only one place, or not at all. Grid planners know this and try to discount for it, but they also face pressure not to fall short, because a shortage of power on a heat-wave afternoon is far worse than a surplus. When planners lean toward building more, and the bills for that cushion are spread across all customers, households effectively provide insurance to an industry that is placing speculative bets.
There is also a timing mismatch. A data center can be built in a year or two. A transmission line can take ten years from proposal to operation, and a new power plant several years. The grid is being asked to plan for a customer that moves at software speed with tools designed for the pace of steel and concrete.
The industry's case, stated fairly
The companies building data centers and their defenders make several reasonable points.
First, data centers are a legitimate customer like any other. Utilities have an obligation to serve, and new demand has historically been welcome because it spreads the fixed costs of the grid over more users, which can lower average rates.
Second, they bring jobs and tax revenue. Loudoun County collects very large property-tax revenue from data centers, which helps fund its schools and services.
Third, many technology companies have signed long-term contracts for clean power and have paid for new wind, solar, battery and even nuclear projects, which add supply and help meet climate goals.
Fourth, capacity prices rose for reasons beyond data centers, including the retirement of older fossil plants and slow approvals for new projects to connect to the grid.
Each point is true in part, and the last one should make progressives uncomfortable. Long waits to connect new clean energy projects to the grid, and slow permitting of transmission lines, are problems our side has sometimes made worse by opposing local projects and stacking up review requirements. If we want cheaper power, we have to want more of it built, faster.
Where the fairness problem lies
Here is my argument.
The usual rule that more customers lower everyone's rates assumes the new customer pays roughly its share of the costs it creates. Data centers break that assumption in three ways.
They are enormous and concentrated. A single campus can require new substations, new transmission lines and sometimes new power plants. Those investments are often built into the general rate base and paid by all customers over decades.
They are uncertain. A company may request a huge amount of capacity for a project that is delayed, downsized or cancelled. If utilities build for that demand and it never arrives, ordinary customers are left paying for stranded equipment.
And they move the regional price. In a capacity market, a surge of demand from one group of customers lifts the price for everyone. A retired teacher in a small Maryland town pays more for capacity because of demand from facilities she will never use.
Meanwhile, the companies driving this demand are among the most valuable in history. They can afford to pay for the grid they need. Asking households already stretched by rent, groceries and insurance to subsidize that buildout is backwards.
Reactors, gas turbines and a reopened island
The scramble for power has produced some remarkable deals. In September 2024, Constellation Energy announced an agreement with Microsoft to restart Unit 1 at Three Mile Island in Pennsylvania, a reactor that had closed in 2019 for economic reasons, and sell its output to the company for twenty years. The unit is not the one that partially melted down in 1979; that was Unit 2. Constellation renamed the plant the Crane Clean Energy Center. A month later, Google announced an agreement to buy power from small modular reactors to be developed by the start-up Kairos Power. Amazon bought a data-center campus next to the Susquehanna nuclear plant in Pennsylvania.
Those deals add carbon-free supply or keep it running, and that is welcome. But they also raise a quieter fairness issue. When a data center connects directly to an existing nuclear plant, it can take power that was previously flowing into the shared grid. In November 2024, federal regulators at FERC rejected a proposal to expand the amount of power the Susquehanna plant could send directly to the Amazon campus, after objections from utilities who argued that other customers would end up paying for grid services the data center would still rely on. The details are technical; the underlying question is the one running through this whole debate. Who carries the shared costs of the system?
Not every project is clean. In several states, utilities have proposed new natural gas plants largely to serve data centers, locking in decades of fuel costs and emissions that households may help pay for long after any one tech company's plans change. Communities near those plants, often working-class and sometimes already burdened by pollution, carry the health costs as well.
Water, land and the towns that host them
Electricity is not the only resource at stake. Many data centers use large amounts of water for cooling, which matters in places like Arizona that are already managing scarce supplies. Others are built on farmland, change the look of rural counties and bring the constant hum of cooling equipment to neighbours who were there first. Local governments often approve projects quickly, drawn by tax revenue, sometimes with non-disclosure agreements that keep residents from learning which company is behind a proposal until late in the process.
None of that means communities should refuse every data center. It means local residents deserve to know who is building, how much power and water the project will use, and who will pay for the infrastructure it requires, before the zoning vote rather than after.
What paying your own way looks like
The good news is that regulators know how to fix this, and several states have begun.
Large-load tariffs. A tariff is the set of rules and prices a utility charges a class of customer. Several states have approved special tariffs for very large new users. In Ohio, regulators in 2025 approved a plan for AEP Ohio that requires new data centers to pay for a large minimum share of the power they reserve for years, even if they end up using less. That protects other customers if the projects shrink. Virginia regulators have created a separate rate class for the biggest users. These are not radical measures; they apply ordinary utility principles to an unusual customer.
Pay for the wires. When a data center requires new transmission or substations, the costs can be assigned directly to that project rather than spread across the system.
Bring your own power. Some proposals would let or require data centers to supply their own new generation or storage, ideally clean, so they add to the grid's capacity rather than drawing it down. That also speeds up clean energy deployment.
Flexibility. Data centers can sometimes shift or reduce their use during peak hours. Researchers have argued that even modest flexibility could let the grid absorb much more new demand without building as much expensive capacity. Paying data centers to be flexible, or requiring it as a condition of connection, could lower costs for everyone.
Transparency. Utility regulators should require public reporting of how much capacity data centers have requested, how much they use and what share of system costs they pay. Without the numbers, families cannot judge whether the deal is fair.
A politics that crosses lines
Electric bills are one of the clearest pocketbook issues there is. Rising power costs became a central argument in the 2025 races for governor in New Jersey and Virginia, both inside PJM's territory. Voters of every party pay electric bills, and very few of them want to subsidize tech giants.
That opens a real opportunity for cross-party work. Rural Republicans in data-center counties worry about farmland, water use and noise. Suburban Democrats worry about bills and climate. Consumer advocates, union electricians who build the grid, and climate groups can all agree on a principle: growth is welcome when it pays its own way and adds clean power, and unwelcome when it raises everyone else's costs.
The alternative is a backlash against all new electricity demand, including the heat pumps, electric cars and factories that a cleaner economy needs. Progressives should want the grid to grow. We should insist that the biggest beneficiaries carry the biggest share of the cost.
What you can do
- Read your bill and show up. Your state utility commission holds public hearings on rate cases and large-load tariffs; a resident's comment about a household budget carries weight with commissioners.
- Ask your state lawmakers one question. Do data centers in your state pay the full cost of the grid upgrades they require? Find your state legislators and ask them to support large-load tariffs and public reporting.
- See where your power comes from. The climate data page shows the US power mix and clean power by state, a useful baseline when a utility says it needs new plants.
- Track the cost of living. Electric bills sit alongside rent and food in the affordability coverage, and the companies building the data centers are followed on the big tech page.
- Join a group that intervenes in rate cases. Consumer and environmental organizations formally participate in utility proceedings; the organizations directory can point you to them in your state.